Programme Update: October/November 2017
McLaren made good progress on the piled foundations in October. We have also completed small drainage alterations and rain water attenuation for the new building.
During November we intend to complete the piled foundations and commence the basement excavation. We will be continuing with the rain water attenuation and forming concrete bases for the two cranes.